NCPI SUPPLIES Ø26’ X 28’, 9MW SAG MILL FOR THE BOMBORÉ GOLD EXPANSION PROJECT IN BURKINA FASO

NCPI SUPPLIES Ø26’ X 28’, 9MW SAG MILL FOR THE BOMBORÉ GOLD EXPANSION PROJECT IN BURKINA FASO

Mill installation in Burkina Faso
At NCP International (NCPI), we pride ourselves on delivering high-quality grinding mill solutions on time and to stringent performance standards. Our recent contribution to the Bomboré Gold Project expansion in Burkina Faso is another example of our commitment.

The project involved the supply of a Ø26 x 28ft, 9MW SAG mill—a key piece of equipment for the client’s ongoing growth.

Having previously collaborated with our client, NCPI was entrusted to deliver a reliable and efficient milling solution. Our existing relationship meant expectations were clearly aligned from the outset, enabling smooth execution from engineering to delivery.

All components of the SAG mill were delivered to the highest standards of quality. Whether refurbished or newly manufactured, every item was subjected to rigorous inspection and backed by OEM-level assurance, ensuring that every part met our strict technical and performance benchmarks, contributing to a robust and efficient final product.

NCPI coordinated the global sourcing, engineering, and shipment of over 1,250 tons of equipment to site. Thanks to detailed planning and execution, all critical components were delivered within 25 weeks—a result made possible by NCPI’s experienced team and streamlined project management approach.

A Trusted Supplier in Global Mining
This successful delivery reflects NCPI’s unwavering focus on quality workmanship, timely execution, and customer satisfaction. We remain committed to supporting our clients with dependable solutions that meet the demands of modern mining operations.

As installation has begun, the SAG mill stands ready to play a key role in the project’s continued success.
35 tonne mill head sections being delivered to port for shipment
45 tonne mill trunnions, re-machined to revised design specifications suiting the new SAG Mill application
9MW slow speed synchronous motor rebuild and Factory Acceptance Tested
A LANDMARK PROJECT FOR THE NCPI TEAM

A LANDMARK PROJECT FOR THE NCPI TEAM

NCPI secured the order from Swakop Uranium to supply the new Grinding Mill package for the Husab project in 2013, the project was installed a year later.

The contract included for the supply of a new 36’Ø x 19.5′, 13.5 MW Primary SAG Mill and a new 22’Ø x 34′, 8.5 MW Ball Mill..

The SAG Mill was designed to accept Primary crushed ore at F100-250mm from the primary stockpile and process the material in open circuit. The primary mill liner design allowed for pebble porting and a dedicated scats crushing circuit processing the ejected +80mm material and recycled this back to the SAG mill feed.

The Ball mill operated in closed circuit with several vibrating screens, with the circuit designed to treat 1875tph of Uranium ore delivering a product of P80-350um.

Both the SAG Mill and the Ball Mill were supplied as dual drive mills carrying full VSD capability, through supply of two ACS6000 VVVF Drives. The drives were designed to start the mills in a controlled fashion and allow the mill operation at a preselected speed to optimize the grind and the final product size distribution. The drives were supplied with creep capability including auto positioning to allow inching of the mills to a preselected position by using the main drive motors. In accordance with NCPI’s specification and the client’s preference, both mills also carried mechanical inching drives.
NCPI’s contract included for the design and manufacture of the mills, transport to the mine site which is located around 40km east of Swakopmund in Namibia and the full installation contract.

The site conditions defined the maximum site temperature more than 40deg C, which required the mill motors and Variable Speed Drives to be water cooled. NCPI’s contract included for the design, supply and installation of a complete water chilling and distribution circuit.

The mills were successfully commissioned in 2016, completing the entire design, manufacture, delivery to site on time within 50 weeks. The mills have been successfully running since 2016, with full after sales and technical support offered by NCPI.

“This was a landmark project and is believed to be amongst the largest gear driven mills operating in Africa. Another successful project completed on time and on budget by NCPI.”

NCPI SUPPLIES ONE OF THE LARGEST GEAR DRIVEN MILLS EVER MANUFACTURED

NCPI SUPPLIES ONE OF THE LARGEST GEAR DRIVEN MILLS EVER MANUFACTURED

NCPI successfully completed the supply of one of the world’s largest gear driven mills ever manufactured for RED 5’s KING OF THE HILLS (KOTH) gold project in Australia.

NCPI was awarded this contract by Engineering, Procurement and Construction (EPC) firm MACA Interquip and has delivered on all contractual commitments made during the lead up to the order placement.

The company supplied the KOTH project with a 36’Ø x 17,5′, 18 MW, Dual direct Drive Bi-directional Semi-autogenous (SAG) mill supported off multi-pad hydrostatic trunnion bearings.

The direct drive mill excludes the gearboxes, with the two main drive synchronous motors controlled by an ABB VVVF (Variable Voltage, Variable Frequency Drive) and directly coupled to the pinion shafts via torque limiting couplings. The duty of the mill is to grind Run of Mine (ROM) material fed at a rate of 500TPH from the primary crushing circuit at a F100 material size of 320mm, delivering a product of P80-150µm.

The Mill start sequence via the ACS6000 Variable Speed Drive ensures a controlled Mill start with locked-charge protection, which protects the mill structural integrity at all times. The Mill Drive train is designed to allow Mill Inching for mill maintenance purposes and includes the advantage of automatic Mill positioning to optimize relining functions.

NCPI’s scope of work included the supply of the mill, delivered CIF to Freemantle port, Western Australia, and included installation supervision and commissioning assistance.

“The SAG Mill’s delivery time frame was critical for this project.”

NCPI committed to an ex works delivery time frame of 38 Weeks from order. NCPI achieved on-time delivery, including meeting shipment delivery time frames despite the COVID19 pandemic. NCPI is proud to have met the client’s expectations in this regard.

The mill installation is 95% complete with commissioning planned to commence in March 2022. Installation has run to schedule with NCPI providing the onsite Mill Installation supervision services. NCPI will supply the client full aftermarket sales service, on-site service and technical support through our local partners.

“NCPI is pleased to have successfully completed this mill supply following two other successful mill installations into the Australian market.

STANDING THE TEST OF TIME

STANDING THE TEST OF TIME

In 1986 Osborn supplied two 14’Ø x 22’ shell-supported ball mills for a gold project located in Stilfontein, South Africa. The plant was shut in 2012 and NCPI purchased the mills in 2017 together with a three-stage crushing circuit.
In 2019, NCPI was awarded the contract for the supply of two 14’Ø x 22’ refurbished shell-supported ball mills for a client in Northern Zimbabwe. Based on the client requirements and the redundant stock NCPI had available, an agreement was reached to supply the mine with re-engineered and refurbished mill components.

NCPI’s scope of supply included the MV switchgear together with liquid resistance starters and mill main motors. Several upgrades were completed including:

  • Changes to the ratio of the main reducers to increase the speed of the mill and allow increased power draw within the design limitations of the existing drive train.
  • Manufacturing new discharge endplates for a heavier cantilevered load required for the new trommel screen.
  • Changing the liner design from a grate discharge to an overflow discharge arrangement.

On completion of the mill refurbishment, NCPI transported the mill components from Johannesburg, South Africa to the mine in Northern Zimbabwe. NCPI’s installation team were on site to supervise and assist with the installation and upskill of the local labour, teaching them the necessary skills required for mill installation and maintenance.

The re-engineered and refurbished components completed under NCPI’s quality control allowed us to provide a warrantee equivalent to that of new equipment.

The mills were successfully commissioned in 2021, completing the entire design, manufacture, delivery and installation cycle. The mills are operating successfully with full after-sales, technical support, and regular maintenance inspections being undertaken by NCPI.
PAVING OUR WAY IN BURKINA FASO

PAVING OUR WAY IN BURKINA FASO

“Just like many of our previous projects, the Bombore Gold project is yet another one for the record books. This mill was installed on site in Burkina Faso under a challenging timeframe, and yet NCPI still managed to deliver the project on time and within budget. This marks yet another NCPI Mill supplied into West Africa, with our West-African Technical support partner offering after sales technical support for the life of the mill.”- Brian Mills (NCPI’s Managing Director).

In 2021, NCPI was awarded the contract for the supply of a new 17’Ø x 25’, 3.2 MW Ball Mill which included the mill control panel and supply of the VVVF VSD for main drive motor.

NCPI fulfilled all our commitments made at sales stage, and completed the mill design, manufacture, and supply of selected critical spares.

NCPI was subsequently appointed as the mill installation contractor by Lycopodium Minerals, who were appointed by Orezone Gold Corporation as the EPCM company managing this project. NCPI was also contracted to supply the mill installation tooling for the project and will be providing commissioning assistance services to our client.
The Bombore Project once again emphasises that NCPI has developed into a global leader in new grinding mill Supply and, no matter your project challenges, NCPI will find a way to deliver a successful project to our ever-expanding client base.
SOPHISTICATION IN MILLING

SOPHISTICATION IN MILLING

Caledonia Project

As you may have read in our last blog, NCPI recently supplied a 17’Ø Ball mill into Burkina Faso for the Bombore Gold Project, allowing us to not only cement our position in Burkina Faso, but also to increase our footprint throughout Africa.

NCPI designed, manufactured, supplied, and commissioned a new 12’Ø x 18’, 1.25 MW Ball mill over the same period for a brownfields project in Gwanda District in Zimbabwe, including supply of critical and operational spares. This brings the total number of NCPI milling projects supplied into Africa to 220 with several African projects in production at present.

NCPI provided technical support and guidance to the client and included a PLC for the control & monitoring of this milling station.

For this project, lead time was significantly critical, and NCPI did achieve an amazing delivery time of 24 Weeks EXW for a new mill, living up to all our commitments made during the sales stage of the project.

When all is said and done, one of the biggest compliments we can receive is an email after commissioning the mill, from our client, that reads:

“It was a pleasure working with you guys – including Manie, Barry, Craig and Stef – and all the people we never met. You made it easier for us by your high standards and consistency to accuracy. You brought to us sophistication in milling, and while it is a challenge, it is an exciting piece of equipment that will we are very confident will help us achieve our targets.” – Cavin Magwenzi
(Engineering Manager Caledonia Mine)

NCP will be offering full after sales support and technical assistance on this project, and we look forward to maintaining our relationship with the client going forward.

Embedded in the culture of day to day running at NCPI and Illustrated in the picture below – “Through teamwork, Everything Is Possible”.